On September 28, 2022, Wellons.RU LLC completed a project to replace the refractory lining of the flat roof of the boiler as part of the modernization project for the furnace of steam boiler No. 1 at a mini-CHP. These works were carried out under the terms of the EPC contract, including engineering, selection and supply of materials, as well as work on breaking out the existing (old) lining and lining work on the installation of a new refractory lining ...
At 22:00 on October 03, 2022, when the temperature reached 750°C, the boiler automation reached the temperature shelf provided for by the ignition schedule by the manufacturer. After holding the temperature shelf for 7 hours, namely at 5:00 on October 04, 2022, the boiler left the ignition schedule. From 05:00 on October 04, the boiler is in the industrial technical operation mode and operates ...